110 kV line
Görries-Hagenow

Client: LTB Leitungsbau GmbH

End customer: Wemag


GVS-Energie is pleased with the rammed pipe and slab foundations as well as pre-assemblies at LTB.


Project key figures:
  • Construction period (week/year): 13/2019 - 26/2019

  • 14 masts founded in pile pipe

  • 9 masts founded with slab foundations

  • 23 masts pre-assembled



Founding:
  • Concrete volume (m³): 710

  • Reinforcement (t): 57

  • Mass UT (t): 30


Steel construction:
  • Pre-assembly mass (t): 194