Successfully implemented projects.
Omexon, Alle
Foundation in difficult soils and heavy substructures up to 35t.
EQOS, Alle
BASF in Schwarzheide is getting a new substation.
LTB, Alle
Pre-assembly and stacking of masts 165A and 49A.
C-TEAM, Alle
With very challenging locations and excavation pits up to 6.50 m deep, we have built on our success with lots D4 and D6.
Another major project for LTB with end customer 50 Hertz was realized within the planned construction period.
BOUYGUES, Alle
Our first contract for the French pipeline construction company BOUYGUES with the establishment of 18 locations.
For our long-standing and reliable customer LTB Leitungsbau GmbH, we have erected 13 masts and installed the lower sections on 16 masts.
The first railway line of GVS-Energie, a project of LTB-Leitungsbau GmbH on behalf of DB-Energie GmbH.
The 380-kV Bertikow-Neuenhagen line is GVS-Energie's largest project in 2021 to date.
110-kV line Görries-Wittenburg
GVS-Energie's most challenging project in 2020.
110-kV line Brachenfeld-Audorf, M93N, M94A
Europten, Alle
The new prequalification procedure at Tennet required for the stagnation was successfully completed on November 3, 2020.
Pre-assembly of 52 masts in difficult terrain in the beautiful Saarland for the client Europten and end customer Westnetz.
Electron, Alle
Our first project at home for our client Electron.
GVS's first 380-kV contract, a TenneT project with rammed pipe foundations, pre-assembly and piling.
A long-term 380-kV 50 Hz large-scale contract in the Wolmirstedt area, large foundation volume.
GVS's first contract, a 110 kV Mitnetz project, foundation, pre-assembly and mast erection.
27 mast replacement construction with slab foundation in the network of Enso Energie Sachsen Ost AG with the client C-Team.
6 masts replacement new building at the same location with slab foundation over the existing foundation.
Pre-assembly of 18 masts in the TEN network with client LTB Leitungsbau GmbH.
Slab foundation foundation work and pre-assembly on a 110 kV Edis line in the Thyrow area.
GVS-Energie is pleased with the rammed pipe and slab foundations as well as pre-assemblies at LTB.
First project for the Europeans: Pre-assembly on the 380 kV Ragow-Preilack line at pylon 110 in March 2019.
34 masts integration of bored piles