380-kV-Ltg. Dörpen/West-Niederrhein

Client: Europten Transmission Germany GmbH
End customer: Tennet TSO GmbH
Erection of eight 380 kV pylons for EUROPTEN GmbH. The new prequalification procedure required for the erection at TenneT was successfully completed on July 23, 2025.
Project key figures:
Construction period: June 2025 to August 2025
Construction period (weeks/year): 25/2020 - 50/2020
8 masts pre-assembled
8 masts stacked
Steel construction
Mass pre-assembled (t): 495
Mass Stocken (t): 495