380 kV line Wahle-Mecklar D3

Client: LTB Leitungsbau GmbH
End customer: Tennet TSO GmbH
For our long-standing and reliable customer LTB Leitungsbau GmbH, we erected 13 masts and installed the base sections for 16 masts. The heaviest base section, weighing 32 tons, on mast D050, was installed by our fitters.
Project key figures:
Construction period (week/year): 08/2021 - 06/2022
13 masts new construction
Founding
Concrete volume (m³): 1,212.50
Reinforcement (t): 47.50
Mass UT (t): 270.50