380-kV-Ltg. Ulzburg-Lübeck West (OKL 1. BA), Los 4 + Los 5

380 kV line Ulzburg-Lübeck West (OKL 1st construction phase), Lot 4 + Lot 5
Client: Cteam Consulting und Anlagenbau GmbH
End customer: Tennet TSO GmbH
Foundation work for cteam of 23 pylons in the first construction phase of the East Coast power line in challenging soils with high groundwater levels and demanding end customers. Second major project for one of our three Brextors at cteam.
Project key figures:
Construction period 04/2023 to 04/2025
23 new masts
6 masts, slab foundations with a total concrete volume of 2,900m³
17 masts, integration of bored pile masts
Founding
Concrete volume (m³) 2,900
Reinforcement (t) 340
UT places (t) 250
Soil replacement (m³) 2,800
68 milled bored piles using the Brextor system