380 kV line Wahle-Mecklar D2

380 kV line Wahle-Mecklar D2
Client: Cteam Consulting and Plant Engineering GmbH
End customer: Tennet TSO GmbH
With extremely challenging locations and excavations up to 6.50 m deep, we built on our success with Lots D4 and D6, completing 22 foundations in 10 months.
Project key figures:
Construction period (week/year): 09/2021 - 06/2022
23 masts new construction
Founding
Concrete volume (m³): 4,087.00
Reinforcement (t): 260.00
Mass UT (t): 567.80