80-kV-Ltg. Ulzburg-Lübeck West (OKL 1. BA), Los 2 + Los 4

Client: LTB Leitungsbau GmbH
End customer: Tennet
Foundation work for LTB of 48 pylons in the first construction phase of the East Coast Line in challenging soils with high groundwater levels and demanding end customers. Second major project for one of our three Brextor towers at LTB.
Project key figures:
Construction period 04/2023 to 04/2025
48 new masts
12 masts, embedding driven piles
2 masts, slab foundations
34 masts, integration of bored pile masts
Founding:
Concrete volume (m³) 1,400
Reinforcement 162.8t
UT places 521t
136 milled bored piles using the Brextor system