top of page

380-kV line
Bertikow-Neuenhagen, Lot 5

380 kV line Bertikow-Neuenhagen + 380 kV line. Nordring Berlin

Client: LTB Leitungsbau GmbH

End customer: 50 Hertz Transmission GmbH


The 380-kV Bertikow-Neuenhagen line is GVS-Energie's largest project in 2021 to date.


Challenge in this project:

"We at GVS-Energie are proud to have been commissioned with the pylon foundations for the new high-voltage line after 15 years of planning. One challenge is the foundation of the 42 pylons within a construction period of 25 weeks. We trust our experienced crew to complete this project within the agreed timeframe."


Jörg Weser (Project Manager GVS-Energie GmbH)


Project key figures:

Construction period (weeks/year): 46/2020-45/2021

  • 45 masts replacement construction with slab foundation

  • 45 UT masts pre-assembled, positioned and aligned


Founding
  • Concrete volume (m³): 5,700

  • Reinforcement (t): 460

  • Mass UT (t): 213

bottom of page