380 kV line
Ganderkessee-St. Hülfe

Client: Europten Transmission Germany GmbH
End customer: Tennet TSO GmbH
The new prequalification procedure at Tennet required for the stagnation was successfully completed on November 3, 2020.
Project key figures:
Construction period (weeks/year): 25/2020 - 50/2020
15 masts pre-assembled
12 masts stacked
Steel construction
Pre-assembly mass (t): 793