380 kV line
Grabowhöfe-Güstrow

Client: Cteam Consulting and Plant Engineering GmbH

End customer: 50 Hertz


Six masts, a new, identically constructed replacement with slab foundations over the existing foundations. The first project with C-Team in the 50 Hertz Transmission network.


Project key figures:
  • Construction period (weeks/year): 32/2019 - 47/2019

  • Foundation of 27 masts (slab foundations)

  • Foundation of 5 masts (slab foundations)

    Pre-assembly of 4 masts



Founding
  • Concrete volume (m³): 1,110.00

  • Reinforcement (t): 186.76


Steel construction
  • Pre-assembly weight (t): 1,110.00

  • Stock mass (t): 186.76