110 kV line
Großräschen-Schwarzheide

Client: Electron Leitungsbau GmbH

End customer: Mitnetz


Our first project in our home country for our client Electron. A replacement construction of the existing high-voltage overhead lines in Großräschen-Schwarzheide and Großräschen-Finsterwalde.


Challenge in this project:

"As part of the new construction of the 110-kV line between Großräschen-Schwarzheide and Großräschen-Finsterwalde, 55 pylons will be newly founded, erected, and aligned. This will provide relief for residents, as the current line runs directly through a residential area and gardens. As part of the commissioning, this line will be dismantled, creating new living space."


Michael Arnold (Project Manager GVS-Energie GmbH)


Project key figures:
  • Construction period (weeks/year): 40/2020 - 13/2022

  • Replacement construction of 60 masts

(18 slab foundations, 42 driven pile foundations, pre-assembly and piling)



Founding
  • Concrete volume (m³): 900

  • Mass of reinforcement (t): 89


Steel construction
  • Pre-assembly mass (t): 500

  • Stock mass (t): 500