110 kV line
Großräschen-Schwarzheide

Client: Electron Leitungsbau GmbH
End customer: Mitnetz
Our first project in our home country for our client Electron. A replacement construction of the existing high-voltage overhead lines in Großräschen-Schwarzheide and Großräschen-Finsterwalde.
Challenge in this project:
"As part of the new construction of the 110-kV line between Großräschen-Schwarzheide and Großräschen-Finsterwalde, 55 pylons will be newly founded, erected, and aligned. This will provide relief for residents, as the current line runs directly through a residential area and gardens. As part of the commissioning, this line will be dismantled, creating new living space."
Michael Arnold (Project Manager GVS-Energie GmbH)
Project key figures:
Construction period (weeks/year): 40/2020 - 13/2022
Replacement construction of 60 masts
(18 slab foundations, 42 driven pile foundations, pre-assembly and piling)
Founding
Concrete volume (m³): 900
Mass of reinforcement (t): 89
Steel construction
Pre-assembly mass (t): 500
Stock mass (t): 500