380-kV line Röhrsdorf-Weide, Lot 2

380 kV line Usterath-Philippsburg (ULTRANET)
Client: LTB Leitungsbau GmbH
End customer: 50 Hertz Transmission GmbH
Another major project for LTB with end customer 50 Hertz was realized within the planned construction period.
Project key figures:
Construction period (week/year): 04/2023 - 10/2023
20 masts new construction
Founding
Concrete volume (m³): 2,400.00
Reinforcement (t): 230.00
Mass UT (t): 99.00