110-kV line Schwarzheide-Großräschen

110-kV line Schwarzheide-Großräschen (BASF)
Client: EQOS Energie Deutschland GmbH
End customer: Mitnetz + BASF Schwarzheide
BASF is getting a new substation in Schwarzheide. For this purpose, three existing pylons were relocated and rebuilt on the BASF site. GVS Energie GmbH provided the foundation and pre-assembly services in-house. Concrete curing for XA3 concrete was carried out in-house on all three slabs.
Project key figures:
Construction period (week/year): 08/2023 to 10/2024
3 mast replacement construction with XA3 post-treatment
Founding
Concrete volume (m³): 245
Reinforcement (t): 28
Mass UT (t): 13
Pre-assembly (t): 66
Dismantling 2 masts:
18t scrap, 55m³ demolition concrete