110 kV line
Selbach-Wadern

Client: Europten Transmission Germany GmbH
End customer: Westnetz
Pre-assembly of 52 masts in challenging terrain in the beautiful Saarland region for the client Europten and end customer Westnetz. Successful completion in December 2020.
Project key figures:
Construction period (weeks/year): 30/2020 - 50/2020
50 masts pre-assembled
Steel construction
Pre-assembly mass (t): 324